The Kanab Municipal Airport has received an API grant to perform a mill and overlay of runway 1/19 and crack seal, top coat and restripe taxiways and aprons. Because of the scope of this project, the airport and runway 1/19 will be close for the 22-day construction period.

Construction start date is September 24, 2018, and will continue through October 13, 2018.

Airport staff asks for the following help:

1. Hangered aircraft, no action required

2. Aircraft parked in the tie-down areas will need to be moved at some point during construction.

Please contact Jeff Turner at 435-644-2299 with the best way to contact you for construction updates and the date your aircraft will need to be moved.

The City of Kanab would like to thank you for your timely response and cooperation in these matters.